PQ 8.325 (AGA)
From SKYbrary Wiki
| Article Information | ||
|---|---|---|
| Category: | USOAP | |
| Content source: | ICAO | |
| Content control: | EUROCONTROL | |
Aerodromes, air routes and ground aids (AGA)
Contents |
Protocol question
PQ 8.325 (AGA) - With regard to requirements for runway overlay specifications, does the State require that procedures for the return of a runway to operational status be addressed?
Guidance for review of protocol question
- Review documented evidence of the requirements
- Evaluate mechanism to ensure effective implementation
ICAO Reference
Annex Standard:
- Annex 14, Volume I - 10.3 Runway pavement overlays - 10.3.1
| The longitudinal slope of the temporary ramp, measured with reference to the existing runway surface or previous overlay course, shall be:
a) 0.5 to 1.0 per cent for overlays up to and including 5 cm in thickness; and b) not more than 0.5 per cent for overlays more than 5 cm in thickness. |
- Annex 14, Volume I - 10.3.3 Recommendation - 10.3.4
| Before a runway being overlaid is returned to a temporary operational status, a runway centre line marking conforming to the specifications in Section 5.2.3 shall be provided. Additionally, the location of any temporary threshold shall be identified by a 3.6 m wide transverse stripe. |
Annex Recommended Practice:
- Annex14, Vol. I
Critical Element: Surveillance & Inspection Obligations (6)
PQ Lack of Effective Implementation (LEI): 43.54%
ICAO Representative Protocol Questions (PQs): Full List